Are you confused about ST3? Curious about the status of a specific station? Here’s a map of the Seattle stations with our current understanding of what has happened to them.
The image below is accurate as of October 16th, 2026.

Sound Transit 3 (ST3) is a system expansion project by Sound Transit that was approved by voters in 2016.
The plan includes light rail extensions to Everett, Tacoma, West Seattle, Ballard, and Issaquah, increased Sounder rail service, and Bus Rapid Transit (BRT) service.
The original completion date of ST3 was 2041. The expected completion date for stations like Ballard if nothing changes is 2060.
Of course! We like this one on MetroDreamin
https://metrodreamin.com/view/VHRsZ3NFRHNMTVdMYXp5a2xVbjFoT3RHb2toMXw0
The Avalon station was cancelled in 2026.
The Sounder N line will be discontinued in 2033.
The Boeing Access Road infill station will be planned, but there is no budget for construction. Sound Transit has not yet provided a date for its completion.
The status of South Lake Union station is unclear.
This station was not included in the map for the 2026 realignment so its status is unclear.